|
NEW JERSEY'S PROMPT PAYMENT
LAW By: John F. Neary, Esq.
On September 1, 2006, New
Jersey's Prompt Payment Law (PPL), N.J.S.A. 2A:30A-1 & 2, went into
effect. It applies to all construction contracts entered into after that date;
it established time constraints for payment of agreed-upon invoices on
both public and private construction projects; and extends down the
construction chain from the prime contractor to a second-tier subcontractor or
supplier.1 When an earned and owed payment is not timely paid,
interest accrues and, under certain circumstances, the unpaid payee has the
right to suspend its work pending receipt of the tardy payment. The billing of
an unapproved change-order request would not be covered by the
PPL.2
Except as herein indicated, the PPL applies to all
contracts for "improvements" to real property regardless of the amount,
ownership or use. The term "improvements" includes: (a) building, altering,
repairing, or demolishing any structure upon, connected with, on or beneath the
surface of real property;3 (b) excavating, clearing, grading,
filling, or landscaping any real property; (c) construction of driveways and
private roadways on real property; (d) the furnishing of construction-related
materials for any of the above purposes, including trees and shrubbery; and (e)
performing any labor upon a structure, including architectural, engineering and
surveying. N.J.S.A. 2A:30A-1.
The following payment procedure is
applicable to construction projects other than a public project on which the
governing body's payment approval is required:
1. If the prime
contractor has properly performed the invoiced work; and 2. If the owner
or the owner's "authorized approving agent" has approved and certified
the prime contractor's invoice for such properly performed work
or if, 20 calendar days after its receipt of such a bill,
the owner fails to issue a written Payment Withholding Notice (PWN) stating the
basis for a non-payment; 3. The owner must pay the prime contractor's
invoice within 30 calendar days of the contractually specified billing
date. 4
N.J.S.A. 2A:30A-2(a). Where governing-body
approval is required for such payments, the aforesaid 20-day default approval
period is not triggered until the public meeting following 20 calendar days of
the billing date. At that time, the bill must be either approved or a written
PWN must be provided to the payee. If the bill is approved, it must be paid in
the next payment cycle. Id. This alternate payment procedure must be defined
in the public body's bid specifications and contract in order to have effect.
Id.
If the work or materials of a first or second tier
subcontractor/supplier has been properly performed and has been "accepted" by
the owner and the parties have not otherwise agreed in writing, the
prime contractor shall pay such subcontractor/supplier and it, in turn, shall
pay its subcontractor/supplier, within 10 calendar days of receipt of
payment, the "full amount" the payor has received for the payee's work.
However, in the case where a subcontractor/supplier has ongoing project work,
the amount owed shall only be payable if the subcontractor/ supplier has
properly performed. N.J.S.A. 2A:30A-2(b). (This protection existed under
the predecessor statute, which bore the same citation as the PPL and protected
only subcontractors.)
The PPL provides that prime construction contracts
and first and second tier subcontracts/purchase orders entered into after
September 1, 2006 shall have a provision that payment disputes thereunder
may be submitted in accordance with an alternate dispute procedure
(ADR). N.J.S.A. 2A:30A-2(f). Although it is unclear as to whether both
parties must agree to such an ADR submission, the analogous ADR requirement of
the Local Public Contracts Law (LPCL) allows for the invocation of ADR by
either party. See N.J.S.A. 40A:11-50. It is likely that the PPL will be
similarly construed.
The PPL contains the following two enforcement
mechanisms:
(1) The unpaid protected payee may charge interest, at the
prime rate (i.e. base rate on corporate loans at large U.S. money center
commercial banks5 ) plus one percent, when an earned and approved
bill is not timely paid, N.J.S.A. 2A:30A-2(c) ; and
(2) The
unpaid protected payee, after giving seven (7) days written notice, may suspend
its work without penalty provided: (a) a PPL required payment was not
made; (b) the protected payee was not provided a written PWN;6 and
(c) the payor is not engaged in a good faith effort to resolve the reason for
withholding payment, N.J.S.A. 2A:30A-2(d).
In order to avoid a
work suspension, the payor should be careful to issue a PWN and proceed
in good faith to try to resolve the obstacle to making payment. Exempt from the
PPL's enforcement provisions are federally funded transportation projects, as
defined in N.J.S.A. 27:1B-3, if application of such provisions would
jeopardize funding due to the owner failing to meet federal standards for
financial management systems, as outlined in 49 C.F.R. 18.20.
N.J.S.A. 2A:30A-2(c) & (d).
The rights, remedies or
protections provided by the PPL are in addition to those provided pursuant to
any other provisions of State law. N.J.S.A. 2A:30A-2(e)(1). To the
extent that the PPL provides greater rights, remedies and protections, the PPL
shall supersede such other provisions. Id. The venue for any civil
action brought to collect payments shall be within the State of New Jersey,
N.J.S.A. 2A:30A-2(e)(2), and the prevailing party shall be awarded costs
and attorney's fees, N.J.S.A. 2A:30A-2(f). Neither this venue
requirement nor the right to attorney's fees applies to an ADR proceeding,
which may tend to promote litigation of claims under the PPL. This problem
could be resolved by providing for the recovery of counsel fees in the ADR
provision in the contract.
The PPL, like its predecessor, is
incorporated into other procurement statutes pertaining to State construction
contracts [N.J.S.A. 52:18A-78.11(b)(3) (N.J. Building Authority) and N.J.S.A.
52:32-2(c)] and contracts entered into under the Public Schools Contracts Law
[(N.J.S.A. 18A:18A-18(c)].
The PPL ought not to be confused with New
Jersey's Prompt Payment Act (PPA), N.J.S.A. 52:32-32, et seq., which
requires payment by a State agency within 60 calendar days of the contractually
specified date or, if no required payment date is specified, 60 calendar days
from the receipt of a properly executed State invoice or 60 calendar days from
the State's receipt of goods or services, whichever is later. N.J.S.A.
52:32-34. The interest rate under the PPA is the rate specified by the
State Treasurer by the 30th day after the end of each fiscal year. N.J.S.A.
52:32-35(a). The State is required to notify the vendor within 30 calendar
days of any defect or impropriety in any invoice or goods or services which
would prevent the running of the 60-day payment period. N.J.S.A.
52:32-36. The State Treasurer could waive interest determined to have
resulted from delinquencies beyond the State's control. N.J.S.A.
52:32-37.
First-tier subcontractors and suppliers on State projects
previously enjoyed the protections of the PPA which, pursuant to, N.J.S.A.
52:32-41, provides that: (1) prior to issuance of a progress payment to a
prime contractor by a State agency, the prime contractor must certify that its
subcontractors or suppliers have been paid the amount due from any previous
progress payment and shall be paid any amount due from the current progress
payment and that there exists a valid basis, under a subcontractor's or
supplier's contract, to withhold payment and, therefore, payment is being
withheld; (2) if the prime contractor withholds payment from a subcontractor or
supplier, it shall provide to such subcontractor or supplier a written PWN
providing a detailed explanation for the withholding; (3) a copy of this
PWN must be sent to the owner and the prime contractor's payment-bond surety;
and (4) if the subcontractor or supplier is not paid within 10 calendar
days after receipt by the prime contractor of payment by the owner for the
billed work and no valid basis exists for the payment withholding, the
subcontractor or supplier shall be entitled to the sum wrongfully withheld,
plus interest at the prime rate plus one percent and court costs. If, however,
payment is determined to have been validly withheld, the prime contractor shall
be entitled to his court costs.
1 The
terms "subcontractor" and "subsubcontractor" are defined so as to include one
who has furnished materials. N.J.S.A. 2A:30A-1. 2 The term
"billing" is defined so as to include a "written approved change order,"
N.J.S.A. 2A:30A-1, implying that a billing for an unapproved change order is
not encompassed by the PPL. Also, this term requires that the payment request
be "in accordance with the terms and definitions of the applicable contract,"
and, generally, construction contracts do not permit an "extra" to be billed
unless a written change order has been issued amending the contract to include
the extra. 3 The term "real property" is defined as "real estate
improved upon or to be improved upon." N.J.S.A. 2A:30A-1. 4 The
"billing date," as used in the PPL, means the contractually specified billing
date. N.J.S.A. 2A:30A-1 (The LPCL requires monthly payment for construction
projects in excess of $100,000. N.J.S.A. 40A:11-16.2). 5 See
http://www.bankrate.com/brm/ratewatch/wsj/PrimeRate.asp 6 The
PPL does not specify a time limitation for the PWN notice to a protected
subcontractor/supplier. In fact, unlike owners, prime contractors and
subcontractors are not required to provide a PWN, except in order to avoid a
possible work suspension.
The purpose
of this alert is to inform our clients and friends of recent developments in
the law. It is not intended nor should it be used as a substitute for specific
legal advice or opinions, as legal counsel may only be given in response to
inquiries regarding particular factual situations.
Info@florioperrucci.com
To be removed from
this list, click here
|